CHAUTARA: The construction of the Bahrabise substation, which is considered important for connecting Sindhupalchok and surrounding districts to the national power grid, has been completed.
There are 160 MVA, 132/11 kV, and 5 MVA power transformers in the substation, with a total capacity of 220/132 kV.
Testing of all equipment at the substation based on Gas Insulated System (GIS) technology has been completed. Another substation of 400 kV is also under construction at Bahrabise, it is said.
Under the leadership of Chilime Hydropower Company, a subsidiary of the Nepal Electricity Authority (NEA), the power of the 120 megawatt Mid-Bhotekosi hydropower project built in Sindhupalchowk will be connected to this substation.
According to NEA, the Bahrabise substation will be charged using the same electricity after the production of electricity from the Mid-Bhotekosi hydropower project.
During the testing of structures and equipment to start electricity generation from the project, the tunnel is currently being repaired after water leaked from it.
NEA Executive Director Kulman Ghising said that the tunnel repair is being done with the aim of completing it by the second week of August.
A high-level delegation, including Ghising, monitored the repair work of the substation, transmission line, and tunnel at Madhyabhotekosi on Saturday and asked the project management and contractor company to complete the entire work before the stipulated time.
In the course of the inspection, Executive Director Ghising mentioned that since the construction of Bahrabise substation, there has been no problem for the electricity generated from the Mid-Bhotekosi to connect to the national grid.
The power generated from the Mid-Bhotekosi Project would be connected to the Bahrabise substation via the 220 kV transmission line.
The NEA Executive Director Ghising said the project has already constructed the tower for the around four-kilometer (220 kV) single-circuit transmission line from the switch yard of the powerhouse up to the Bahrabise substation.
The cable has been stretched over around two kilometers of the transmission line.
According to Ghising, the project has not been able to fix the cable on the remaining two kilometers due to the protest by the locals of Palanti at Ward No. 3 and 4 of Bahrabise municipality.